CHATCOLET MARINA

PROJECT DESCRIPTION

162 slip marina, fabricated steel dock frames, Aluminum gangways, fully assembled with float tubs and rub-strips

Copy of PXL_20260521_195339660.jpg
marina3.png

OVERVIEW

A new 162 slip marina at Heyburn State Park, Id. The project included the docks, a fuel dock and guest dock, a boat launch and an access gangway as well as several signs and other miscellaneous steel.

CHALLENGES OVERCOME

The project included several challenging aspects. The steel frames of the docks were often warped during the galvanizing process and had to be straightened before they could be used. The dock float assembly process was intensive and required care since there were multiple materials being connected together, the steel frames, polytub floats and UHMW rub strips. The 80’ gangway fit up and fabrication required a high level of precision. The fuel and guest docks required considerable coordination with other contractors to ensure that the required equipment would fit and connect properly.