top of page

King County Metro

PROJECT DESCRIPTION

120 Bus Charging Base. Complex coatings, specialty colors, and 100’-0 shipped 1-piece gantries

20251208_095509.jpg
20250808_140012.jpg

OVERVIEW

Project included site scanning, coordination with electricians for preinstallation here at Finnoe, proof of concept construction, specialty miscellaneous metals fabrication.

CHALLENGES OVERCOME

Complex 3D tower fabrication. We designed and built special stands to rotate the gantries like a rotisserie for painting.

Avista Hog Structure

PROJECT DESCRIPTION

81-ton, two story, structure for a biomass generating station.

hog5.jpg
hog6.jpg

OVERVIEW

Supplied structural Steel with connection design, grating, guardrails, and ladders. The project also includes galvanizing, powder-coat, and 3-coat paint system (zinc-rich primer, epoxy, and aliphatic polyurethane)

CHALLENGES OVERCOME

Connections between new and existing building with grating & guardrail system requiring to be design around large equipment required multiple jobsite visits by our in-house detailing team in order to 3-D laser scan current conditions to adjust our steel ensuring a successful installation.

I-90 Floating Bridge Cable Replacement 

PROJECT DESCRIPTION

Design-build powered wire spools for replacing the anchor cables of the I-90 floating bridge on Lake Washington.

cable5.jpg
cable3.jpg

OVERVIEW

Completed the design and fabrication of powered cable spoolers, including gear drives, electrical functionality, and bearings. The project also included fabrication of miscellaneous barge components to retrofit the equipment barge used to pull and replace the cables.

CHALLENGES OVERCOME

An aggressive timeline meant the project couldn’t start until the spoolers were finished. Our team completed the customer’s partial design and began fabricating components while the design was still being finalized. The spoolers were delivered on time and operated as expected without any problems.

Lars Antarctic Platform

PROJECT DESCRIPTION

Three towable design-build sleds that connect into an “H”-shaped hot water drilling platform for the National Science Foundation in Antarctica.

lars1.jpg
lars3.jpg

OVERVIEW

Completed the design from Lockheed Martin’s scope of work and conceptual drawings. The design was structurally analyzed by BBFM Engineers and approved by the customer. The center sled carries a 30-ton hydraulic crane that reaches most of the deck, and both side sleds have removable deck sections for drilling through the ice. Fabrication was contracted to Northwest Steel Fab and managed directly by our team.

CHALLENGES OVERCOME

The extreme cold environment required special considerations throughout the design, including Charpy V-Notch certified steel. The schedule was extremely fast-paced: the contract was awarded on July 9th and the sleds shipped complete on October 16th, 2012. Our team pulled together to deliver a successful project.

bottom of page